Capabilities > Industrial Facilities > Honda - ELP Water System Improvements
Honda - ELP Water System Improvements
Location: East Liberty, Ohio
Project Owner: Honda Of America MFG., Inc.
Bid Amount: $665,932.00
Faced with a deteriorating water line that jeopardized plant operation, the Honda Motor Company contracted Kokosing to replace the line from the existing well field to the plant, as well as provide pipe modifications. Kokosing scheduled its work to coincide with the plant’s scheduled shut down and successfully installed approximately 2,000 linear feet of 12-inch-diameter thermoplastic pressure piping with valves, hydrants and live taps throughout the facility.